ESPR Preparatory study and Impact Assessment support study
|
Date (planned) |
Event/plan |
|
12 March 2026 |
Start of the ESPR Preparatory Study and Impact Assessment support study on furniture |
|
April 2026 |
Launch of the project's online platform |
|
May 2026 |
Launch of the consultation questionnaire |
|
May 2026 |
Start of consultation of registered stakeholders for inputs on the development of the MEErP Task 1-4 reports (i.e. scope, market, users, technologies) |
|
August 2026 |
Interim draft Task 1 to 4 reports for stakeholder comments |
|
6 October 2026 |
First Stakeholder meeting on the MEErP Tasks 1 to 4 for registered stakeholders |
|
Februay 2027 |
Interim draft of Task 5 to 7 reports for stakeholder comments |
|
March 2027 |
Second Stakeholder meeting on the MEErP Tasks 5 to 7 |
|
Spring 2027 |
Finalisation of the ESPR Preparatory Study |
|
July 2027 |
Condition*: drafting of Working documents for the Impact Assessment support study |
|
May 2028 |
Condition*: finalising of the Impact Assessment support study, contractual end of the project |
EU Ecolabel criteria revision
|
Date (planned) |
Event/plan |
|
12 March 2026 |
Start of the study |
|
April 2026 |
Launch of the project’s online platform |
|
May 2026 |
Launch of Preliminary Stakeholder Consultation (deadline: 29 June 2026) |
|
Q1 2027 |
Publication of the Preliminary Report |
|
April 2027 (tbc) |
1 Ad-hoc Working Group (AHWG) meeting |
|
September 2027 (tbc) |
2 Ad-hoc Working Group (AHWG) meeting |
|
Mid 2028 |
Final EU Ecolabel Criteria for furniture |